Summary The City Commission adopted the FY 2018 Strategic Plan on October 9, 2017. Strategic Initiatives 1.1 and 1.2 are to upgrade critical bottlenecking issues in the water and wastewaer infrastructure, respectively.
The primary area where the infrastructure needs exist is near the I-75 and U.S. Hwy 441 intersection, particularly west of I-75. As part of prior year action steps, staff has engaged consultants to assist with modeling and design of improvements that will address this matter. Staff has also secured necessary land rights for future infrastructure.
This presentation will provide background information regarding the current infrastructure network and proposed improvements. Furthermore, the presentation will demonstrate the need for the City to provide master planned infrastructure while ensuring the costs for such improvements are equitably shared by future developments.
|