Summary The Alachua West Utility Project consists of water and wastewater infrastructure improvements. On March 25, 2019, the City Commission awarded RFB 2019-05 to Miller Pipeline, LLC for the utility infrastructure improvements.
Causseaux, Hewett & Walpole (CHW) submitted a Proposal to the City for for Construction Phase Services in the amount of $65,390.00 for the Alachua West Utility Infrastructure Improvements Project.
The Proposal includes the following Services:
- Construction Administration Services - $15,390.00
- Construction Engineering Inspections - $50,000.00
CHW is the Engineer of Record for the Alachua West Utility Infrastructure Improvements Project. CHW has familiarity with the site location, drainage, stormwater management and utilities.
Staff recommends to accept the proposal from CHW for Construction Administration and Construction Engineering Inspection Services for the Alachua West Utility Infrastructure Improvements Project. |